NTP2020-000368/2
After the completion of the preparatory works from April 20, 2022 to August 1, 2022, Szabadkán is the construction of the more than 3,000 m2 production and storage hall also began in Subotica.
Location of the investment: Serbia, 24 000, Szabadka, Magnetna Polja 3, registration number: 14780/15
Construction is carried out according to the schedule specified in the construction contract concluded with ARHI.PRO DOO.
Construction completion rate on July 22, 2024: 100,00 %
The technical inspection tasks of the construction were carried out by the experts of ENERGO KONSTRUKT DOO in Subotica.
A solar panel unit with a capacity of 160 kVA will be placed on the roof of the production and storage hall. Energy is produced for own use.
The shelf system, forklifts and security system have been purchased.